BOND FUND ALLOCATIONS THROUGH 2008 - "One page" edition.

Excerpted from a tracking of Measure A Capital Allocations, the 1991 Spending Plan (known as the "Green Book") through the present. Compiled by Bruce Wicinas, 10/7/94 - 12/16/08. Figures show budgets, not funds expended.       All figures represent thousands of dollars.
SITE
Measure A
'92 Green Book
Measure A
BUSD 2/00
  Description of Projects.
AA
Budgets
A+AA
Jan 2001
Budgets
Jan,
2008

Berkeley High, all projects
47,190 
53,055 
Extensive seismic & systems + rehab of old buildings. Landscaping and new building added.    92,675
94,092
....Modernize G&H

18,420


18,420 18,420
....New buildings/Rehab (D)

27,156


34,300 37,080
....Track & Field

1,707


1,707 1,707
....Old Gym Seismic Rehab
-


20,094 -
....Modernize several buildings

-


7,966  7,899
....Stadium Building

-



10,368
....Gym & Bleacher demo

-



3,780
....Design South of Bancroft

-



2,800
....Ten portables (2008)

-



2,000
....All other BHS projects

5772


10,188 10,038
East Campus ("B-TECH")
1,541 
4,109 
New building.   
5,613
(Alt & E.Campus)
5,498
         
 
Longfellow
4,509 
14,109 
Changed grade configuration. Extensive seismic & systems, rehab of old buildings; New buildings added.   
14,876
17,761
ML King
10,778 
20,259 
Extensive seismic & systems, rehab of all buildings. New dining commons.
 
30,481
36,092
Williard
5,169 
7,521 
Extensive seismic of Gym; rehab of I-building.  
12,532
13,417
         
 
Columbus (now Rosa Parks)
7,899 
12,310 
Old school razed; New school built.  
11,988
12,037
Cragmont
100 
12,869 
Old school razed; New school built.  
12,829
14,796
Emerson
1,578 
2,287 
 Rehab.  
2,939
2,916
Franklin (now The Adult School)
3,038 
3,244 
Budgeted for major rehab - aborted after K-5 school was closed. After 2000, converted to Adult School.
 
9,740
12,958
Jefferson
1,822 
4,858 
Major Rehab.   
5,712
7,093
John Muir
1,153 
1,698 
Rehab.  
2,094
2,664
LeConte
3,545 
3,662 
Modest seismic and rehab  
4,791
4,878
Malcolm X
7,143 
11,456 
Extensive seismic & systems upgrade, rahab of aged school. Improvement of grounds. Flood barrier.
 
11,589
12,404
Oxford
1,588 
2,486 
Rehab.  
3,088
3,092
Thousand Oaks
5,717 
13,622 
Old school razed; New school built.  
13,797
13,873
Washington
6,170 
6,820 
Extensive seismic and rahab.  
7,456
8,166
Whittier / Arts Magnet
5,011 
4,832 
Extensive seismic and rehab.  
5,372
5,736
SUBTOTAL (K-12)
113,951 
179,196 
   
 
Administration Building (Old city hall)
997 
256 
   
256
256
Auxiliary Buildings (Portables);Hillside
826 
 146 
   
240
300 
Auxiliary Projects        
9,495
645
Early Childhood Education
1,309 
1,071 
   
6,780
8,893 
EDC
213 
     
 
"Plant Operations" (Oregon St)
1,771 
362 
   
1,573
673 
Transition Sites
2,200 
     
 
Transportation Offices and Shop
203 
33 
   
33
 13,284
West Campus (the "Adult School")
5,322 
1,004 
   
9,181
15,584 
Furniture        
3,104
SUBTOTAL (Non K-12)
12,841 
2,872 
   
 
SUBTOTL CONSTRUCTION 
126,792 
182,068 
   
 
Certificates of Participation
9,425 
7,531 
   
7531
7,531
Inflation Adjustment
 24,625
1,850 
   
17,282
5,983
Reserve, Contingency, Management, Risk Pool, Deferred Maintenance
0
8,602 
   
Defer 350
Risk 9,938
Mana 5,678
7,182
6,044
Issuance Costs
 1,830
1,217 
   
1,921
1,324
SUBTOTAL (other)
 35,880
19,200 
   
 
         
 
TOTAL PROBABLE COSTS
 162,672
201,268 
   
317,832
338,628
Expected Interest
 (4,682)
(5,574) 
   
11,505
16,216
Bond Funds (A)  (158,000)
(158,000) 
   
150,000
158,000
Bond Funds (AA)        
116,500
116,500
Deferred Maintenance/Other  
(1,403) 
   
3,900
4,396
OLA/OPSC/FEMA Funds  
(34,977) 
   
FE 6,650
OP 20,050
FEMA 6,913
OPSC 34,810
Community and "Other"  
(1,431) 
   
Comm 1,174
Oth 637
BSEP 700
Community 1,167
Other 1,092
TOTAL FUNDS AVAILABLE
 (162,682)
(201,385) 
   
319,116
339,094
Difference
 (10)
(117) 
   
1,284
467

1/12/2008 B.Wicinas